Recently, Mammoet transported an electrical transformer to a high voltage substation for TenneT, a Dutch electricity transmission system operator. Mammoet was able to transport the 325-ton electrical transformer, which was constructed by Royal SMIT Transformers in the Dutch city of Nijmegen, across two of the busiest thoroughfares in the Netherlands while minimizing the delays for travelers.

mammoet-tennet-1

 

MAMMOET MINIMIZES DELAYS FOR TRAVELERS WHILST TRANSPORTING A TRANSFORMER ACROSS TWO BUSY THOROUGHFARES

 

Network expansion
TenneT is currently expanding the electrical grid in the Breukelen-Kortrijk area, situated between the cities of Amsterdam and Utrecht. As part of this expansion, the energy supplier is constructing a new high voltage substation. The electrical transformer, which was built by Royal SMIT Transformers in Nijmegen, will be used to convert electricity from the national grid into the regional grid.

mammoet-tennet-3

 

Important thoroughfares
En route to its new destination, the transformer had to pass over both the railway from Amsterdam to Utrecht and the A2 freeway between these two cities. Because these roads are two of the most important traffic arteries in the Netherlands, traffic disruptions had to be kept to a minimum. Mammoet therefore came up with a two-phase plan that reduced delays for travelers as much as possible.

mammoet-tennet-7

Phase 1
The first phase was executed during the weekend of September 24th . The transformer was shipped to the Amsterdam-Rhine Channel, which runs next to the railway and freeway from Amsterdam to Utrecht. After arrival at the channel, the transformer was lifted from the inland vessel and positioned behind the channel dike by two floating cranes. From there, a Mammoet crawler crane subsequently lifted the transformer over the railway track. This part of the operation was executed between 1 AM and 5 AM to minimize railway delays.

mammoet-tennet-8

The transformer was then lifted onto several SPMTs, which drove it across a pasture and onto the A2 freeway. Through careful preparation, Mammoet was able to move the transformer over the freeway in approximately 15 minutes, keeping the amount of time that the freeway was closed to a minimum.

mammoet-tennet-6

 

Phase 2

The second part of the transport took place in the weekend of October 8th. The transformer was first transported across the A2 freeway from Utrecht to Amsterdam on SPMTs. It then continued its path to the high voltage substation over the A2 from Amsterdam to Utrecht.

mammoet-tennet-5

The SPMTs left the freeway via an exit that was specially constructed for the transformer. The exit – a 125 meter steel ramp – had been specially designed and constructed by Mammoet to safely bridge the height difference between the freeway and the high voltage station.

The electrical transformer is currently positioned next to the high voltage station. It will be installed inside the station once construction of the foundation has been completed.

mammoet-tennet-4

 

 


Find out what products and services CraneMarket has for your business.
e.g. Boom Lifts-Telescopic Cranes for Sale and Rent

Continue to our shop section to browse all cranes for sale
e.g. Crawler Cranes for Sale and Rent

We have so many cranes for rent! Check them now.
e.g. All Terrain Cranes for Sale and Rent